| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| Elementary School #19 | 17,200,000 | 17,200,000 | June 2009 | August 2010 / On Target | ||
| Elementary School #20 | 18,250,000 | 18,250,000 | June 2010 | August 2011 / On Target | ||
| Middle School #6 | 28,150,000 | 28,150,000 | August 2008 | August 2011 / On Target | ||
| Total New Schools | 63,600,000 | 0 | 63,600,000 | |||
| Planning for High School #4 | 4,000,000 | 6,360 | 3,993,640 | August 2008 | January 2010 / On Target |
| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| CHS Science Labs and Band Hall | 3,340,000 | SHW / Brath | 123,539 | 3,216,461 | July 2008 | August 2010 / On Target |
| Career Academies | 5,000,000 | 22,409 | 4,977,591 | July 2008 | November 2009 / On Target | |
| PHS Renovations - Band Hall, Science Labs, Theater Arts | 9,980,000 | PBK Architects | 444,188 | 9,535,812 | July 2008 | August 2010 / On Target |
| Total Student Instruction - Facility Improvements | 18,320,000 | 590,136 | 17,729,864 |
| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| Projectors, Ceiling mounted, Elementary and Middle Schools | 2,500,000 | 220,000 | 2,280,000 | September 2008 | August 2010 / On Target | |
| Model Technology School Pilot | 775,000 | 545,014 | 229,986 | September 2008 | May 2010 / On Target | |
| Video Distribution Upgrade | 225,000 | 225,000 | September 2008 | December 2009 / On Target | ||
| Computer Replacement Cycle | 4,000,000 | 813,724 | 3,186,276 | June 2008 | August 2010 / On Target | |
| Total Student Instruction - Technology Improvements | 7,500,000 | 1,571,979 | 5,928,021 |
| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| Security Systems Update (District-wide) | 100,000 | 119,053 | -19,053 | June 2008 | August 2008 / Complete | |
| Video, Fire and Security System (all campuses) | 3,128,000 | 75,029 | 3,052,971 | September 2008 | August 2009 / On Target | |
| Mobile Communications System Standardization | 180,000 | 86,443 | 93,557 | July 2008 | December 2009 / On Target | |
| Total Safety and Security | 3,408,000 | 280,525 | 3,127,475 |
| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| HVAC Systems Upgrade and Replacement | 7,379,000 | SHW / Brath | 704,364 | 6,674,636 | June 2008 | December 2012 / On Target |
| Parking Lots at CHS and PHS | 240,000 | 203,497 | 36,503 | June 2008 | August 2008 / Complete | |
| Tennis Court Lighting at CHS and PHS | 740,000 | 542,098 | 197,902 | June 2008 | January 2009 / Complete | |
| Restroom Facilities for Softball, Baseball and Tennis Courts at CHS | 1,000,000 | 271,010 | 728,990 | July 2008 | August 2009 / On Target | |
| Renovate Building Annex at PES | 300,000 | 28,276 | 271,724 | June 2008 | August 2009 / On Target | |
| Replace Exterior Doors at PMS | 80,000 | 80,752 | -752 | July 2008 | January 2009 / Complete | |
| Replace Exterior Doors at WVMS | 100,000 | 99,973 | 27 | July 2008 | January 2009 / Complete | |
| Upgrade Fine Arts Center Lighting at PHS | 50,000 | 63,360 | -13,360 | June 2008 | August 2008 / Complete | |
| Total Building Renovations | 9,889,000 | 1,993,330 | 7,895,670 |
| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| Network Operating Center | 2,200,000 | 2,200,000 | January 2009 | December 2009 / On Target | ||
| Network Equipment Upgrade | 1,000,000 | 7,917 | 992,083 | January 2009 | December 2009 / On Target | |
| Server and Storage Upgrade | 1,250,000 | 1,250,000 | September 2008 | August 2010 / On Target | ||
| Wireless Network | 650,000 | 650,000 | January 2009 | December 2009 / On Target | ||
| Voice over IP (Admin. & Support Serv. plus new ESD building) | 500,000 | 47,052 | 452,948 | July 2008 | August 2009 / On Target | |
| Total Technology Infrastructure | 5,600,000 | 54,969 | 5,545,031 |
| Description | Budget | Architect / Contractor | 2007-09 Expenses | Balance | Start Date | Project Status |
|---|---|---|---|---|---|---|
| Future School Sites | 8,500,000 | 2,499,308 | 6,000,692 | On Target | ||
| Contingency | 3,000,000 | 3,000,000 | On Target | |||
| Bond Issuance Costs | 1,183,000 | 935,319 | 247,681 | Complete | ||
| Total 2007 Bond Program | 125,000,000 | 7,637,520 | 117,362,480 |