Pflugerville ISD 2007 Bond Budget Tracking

New Schools

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
Elementary School #19 17,200,000     17,200,000 June 2009 August 2010 / On Target
Elementary School #20 18,250,000     18,250,000 June 2010 August 2011 / On Target
Middle School #6 28,150,000     28,150,000 August 2008 August 2011 / On Target
Total New Schools 63,600,000   0 63,600,000    
Planning for High School #4 4,000,000   6,360 3,993,640 August 2008 January 2010 / On Target

Student Instruction - Facility Improvements

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
CHS Science Labs and Band Hall 3,340,000 SHW / Brath 123,539 3,216,461 July 2008 August 2010 / On Target
Career Academies 5,000,000   22,409 4,977,591 July 2008 November 2009 / On Target
PHS Renovations - Band Hall, Science Labs, Theater Arts 9,980,000 PBK Architects 444,188 9,535,812 July 2008 August 2010 / On Target
Total Student Instruction - Facility Improvements 18,320,000   590,136 17,729,864    

Student Instruction - Technology Improvements

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
Projectors, Ceiling mounted, Elementary and Middle Schools 2,500,000   220,000 2,280,000 September 2008 August 2010 / On Target
Model Technology School Pilot 775,000   545,014 229,986 September 2008 May 2010 / On Target
Video Distribution Upgrade 225,000     225,000 September 2008 December 2009 / On Target
Computer Replacement Cycle 4,000,000   813,724 3,186,276 June 2008 August 2010 / On Target
Total Student Instruction - Technology Improvements 7,500,000   1,571,979 5,928,021    

Safety and Security

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
Security Systems Update (District-wide) 100,000   119,053 -19,053 June 2008 August 2008 / Complete
Video, Fire and Security System (all campuses) 3,128,000   75,029 3,052,971 September 2008 August 2009 / On Target
Mobile Communications System Standardization 180,000   86,443 93,557 July 2008 December 2009 / On Target
Total Safety and Security 3,408,000   280,525 3,127,475    

Building Renovations

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
HVAC Systems Upgrade and Replacement 7,379,000 SHW / Brath 704,364 6,674,636 June 2008 December 2012 / On Target
Parking Lots at CHS and PHS 240,000   203,497 36,503 June 2008 August 2008 / Complete
Tennis Court Lighting at CHS and PHS 740,000   542,098 197,902 June 2008 January 2009 / Complete
Restroom Facilities for Softball, Baseball and Tennis Courts at CHS 1,000,000   271,010 728,990 July 2008 August 2009 / On Target
Renovate Building Annex at PES 300,000   28,276 271,724 June 2008 August 2009 / On Target
Replace Exterior Doors at PMS 80,000   80,752 -752 July 2008 January 2009 / Complete
Replace Exterior Doors at WVMS 100,000   99,973 27 July 2008 January 2009 / Complete
Upgrade Fine Arts Center Lighting at PHS 50,000   63,360 -13,360 June 2008 August 2008 / Complete
Total Building Renovations 9,889,000   1,993,330 7,895,670    

Technology Infrastructure

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
Network Operating Center 2,200,000     2,200,000 January 2009 December 2009 / On Target
Network Equipment Upgrade 1,000,000   7,917 992,083 January 2009 December 2009 / On Target
Server and Storage Upgrade 1,250,000     1,250,000 September 2008 August 2010 / On Target
Wireless Network 650,000     650,000 January 2009 December 2009 / On Target
Voice over IP (Admin. & Support Serv. plus new ESD building) 500,000   47,052 452,948 July 2008 August 2009 / On Target
Total Technology Infrastructure 5,600,000   54,969 5,545,031    

Other

Description Budget Architect / Contractor 2007-09 Expenses Balance Start Date Project Status
Future School Sites 8,500,000   2,499,308 6,000,692   On Target
Contingency  3,000,000     3,000,000   On Target
Bond Issuance Costs 1,183,000   935,319 247,681   Complete
Total 2007 Bond Program 125,000,000   7,637,520 117,362,480